Thursday 27 September 2018

Microsoft Project - Customising Reports




Customising Reports

Reports can be customised where the report can be seen.

1.     To display the reports go to Menu Reports, Reports

2.     Select the category of reports required


3.     Select the report and then click on the edit button.

This gives you information as to how the report is put together.

The definition is where the main details of the report are. In this example the report shows which resource is working on which task when. From the definition the report is broken down on a day by day basis. It can be changed to weeks, months qtrs etc.
Details and Sort will allow you to fine tune the report as necessary.

4.     Make the adjustments as necessary.


 5.     OK the changes. This takes you back to the previous screen.
 6.     Select the report to view the changes.





By changing the existing reports they can still be accessed via the five categories of reports.

No comments:

Post a Comment