Creating Base Calendars
The Project might need more than one calendar.
• Sometimes certain resources work different hours to others.
• The project might be a multinational project
•
Certain tasks can only be done
at certain times
As many calendars as necessary can be
created. The calendars created will only be in the project file they are
created in. They can be copied over to other project files or to the standard
template.
To create a new base calendar
1.
Menu, Tools, Change Working Time
2.
Click on the New Button
The new calendar can be a totally new calendar or a
copy of an existing calendar. It depends on whether the non working time that
has been set for one calendar need to be applied to the new calendar or not.
The calendar needs to be given a relevant name and
then once the calendar has been OKed, then the changes required to the calendar
can be made as discussed before.