Durations
When the task names are entered an
automatic duration is entered against each task. The automatic duration is of
the value of one day whatever unit it is displayed in. There is also a question
mark at the end. The question mark represents that the duration is estimated.
The units of duration are
m minutes
h hours
d days
w weeks
mo months
The duration of each task is entered
into the duration column as a value followed by a unit letter. When entering
durations in the default unit the unit letter does not need to be entered at
the end of the value as it will be assumed automatically.
It can be changed via the Tools, Options Menu.
The duration is measured in working time
only. The value is that that is set in the Tools, options, Calendar Tab
If the duration needs to go into the
non-working time, overnight or the weekend, then the duration can be prefixed
by e for elapsed so that the working time can be ignored. A week is forty
hours, an elapsed week (1ew) is Monday at 8:00 till the following Monday at
8:00