Update Project
If the project (or part of the project
is going according to schedule then the tasks do not need to be updated
individually. The whole of the project (or part, if only some of the tasks are
going to schedule) can be updated in one go.
Menu, Tools, Tracking, Update Project
Here the tasks can be updated up to a
particular date. The date that is entered automatically is the current date (as
defined by the Project Information Dialog Box). This date can be accepted or
changed as required.
% complete options depend on whether the
percentage values are of use or not. The default option will show the
percentages.