Linking Tasks
When entering tasks initially they all
start on the same day. The finish date is dependent on the durations entered
against each one. Rarely on a project do all the tasks start on the same day,
they are more likely to dependent on one task finishing before the next task
can start. To carry this out the tasks have to be linked. There are many ways
of linking tasks- the method that you use is the one that you find most
convenient.
The button
Select the two tasks to be linked and click on the
link button
If several tasks in consecutive cells
all follow on from one another in sequence they can all be selected before the
click on the link button.
If the tasks to be linked are not next
to each other (i.e. non-contiguous) - select the first task as normal and hold
down the ctrl key when selecting the other tasks to be linked. Once all the
tasks to be linked have been selected let go of the ctrl key before clicking on
the link button.
Mouse
Point to the first task and get the four headed arrow, then drag to the task that the original task is succeeded by. - this will bring up a description box showing which task is linked to which - once the information in that box is correct let go of the mouse button.
Entry in
the table -‐ predecessors column.
In the predecessors column type in the id number of
the task that precedes the current task. If there are multiple predecessors,
separate them by commas.
The Different types of Link
The links that have been generated so
far have all been of the standard type. This is not always the case. There are
four different types of link that can be generated.
1.
Finish
to Start (FS)
This is the standard type of
relationship where one task finishes and the second task starts. If the first
task does not finish when required it will cause a delay as to when the second
task can start.
2.
Start
to Start (SS)
The start to start relationship sets it
up so that the starting point of the second task is dependent upon the starting
point of the first task, and if that is postponed for any reason the second
task will also be delayed automatically.
3.
Finish
to Finish (FF)
The finish to finish relationship has
the two tasks finishing together and the second task cannot finish until the
first task finishes.
4.
Start
to Finish (SF)
The relationship of this type of link is
slightly more complex. The starting point of the first task is controlling the
finishing point of the next task. (notice the direction of the link line)
Setting the different types of relationship
Changing the type of link cannot be done when
setting up the link using the link button.
Mouse
Once the link has been established.
Double click on the link line. The dialogue box below will appear on the screen
From the drop down next to the Type box select the
type of link required.
Entry in the table - predecessors column
When entering the id number
in the predecessor column follow the number with the two character code for the type of link required. When a
simple finish to start link is required the code is not required as it is
automatically assumed.
The Task Information Dialog Box
When the preceding task information is
entered into this dialogue box the information on the type of link can be
altered in the next column along - again choosing from a drop down menu.
No comments:
Post a Comment