Microsoft Project - Task - Information Dialog Box

The Task Information Dialog box 


1. Double click on the task



this brings up the task information box.  Across the top there are several tabs -

2. Select the predecessors tab

3. Click in the cell underneath the column heading task name.

4. Click on the drop down arrow on the entry bar in the dialogue box.

5. Select the task that precedes the selected task.

6. If there are multiple predecessors - work down the column to put them all in